24 Apr Weekend Utility Relocation Work Continues for 3rd Street Tunnel Project along Massachusetts Avenue and H Streets, NW, April 25

Traffic pattern changes and closures to occur for five months; expect detours and delays (Washington DC) The District Department of Transportation (DDOT) and Property Group Partners today remind motorists of additional road closures for the utility relocation work of the 3rd Street Tunnel project along Massachusetts...

Read More

24 Apr Lane Reduction, Speed Restrictions on Highway Portion of I-395/3rd Street Tunnel set to begin on Saturday, May 2

Commuters should anticipate delays due to the reduction of one lane on the 2nd Street Off-Ramp to Massachusetts Avenue, NW (Washington, DC) The District Department of Transportation (DDOT) and Property Group Partners (PGP), the developer for the 3rd Street Tunnel project, will institute a single-lane closure...

Read More

24 Apr Construction Update/Look Ahead

Following is the construction Look Ahead, Weekly Forecast, for the Third Street Tunnel Infrastructure Project which outlines work activities that may impact the surrounding community, as provided by Property Group Partners (PGP). Balfour Beatty Construction DC, the construction manager, will make every effort to advise PGP...

Read More

17 Apr Construction Update/Look Ahead

Following is the construction Look Ahead, Weekly Forecast, for the Third Street Tunnel Infrastructure Project which outlines work activities that may impact the surrounding community, as provided by Property Group Partners (PGP). Balfour Beatty Construction DC, the construction manager, will make every effort to advise PGP...

Read More

13 Apr Construction Update/Look Ahead

Following is the construction Look Ahead, Two Week Forecast, for the Third Street Tunnel Infrastructure Project which outlines work activities that may impact the surrounding community, as provided by Property Group Partners (PGP). Balfour Beatty Construction DC, the construction manager, will make every effort to...

Read More

18 Nov Phase 2 of the Third Street Tunnel Utility Relocation Project along Massachusetts Avenue and H Street NW will Begin Tuesday, November 18, 2014

Crews to Work Overnight November 17, 2014 (starting at 7 pm) to implement Traffic Pattern Shift – Expect Detours (Washington D.C.) The District Department of Transportation (DDOT) announces that Phase 2 the Third Street Tunnel Project for utility relocation work along Massachusetts Avenue and H Street...

Read More