Construction Update/ LookAhead

Third Street Tunnel

03 Nov Construction Update/ LookAhead

TRAFFIC & ONGOING UTILITY RELOCATION CONSTRUCTION      

Following is the Construction Look Ahead/Weekly Forecast, for the Third Street Tunnel Infrastructure Project which outlines work activities that may impact the surrounding community, as provided by Property Group Partners (PGP). Balfour Beatty Construction DC (BBCDC), the construction manager, will make every effort to advise PGP of changes that affect the scheduled events. The schedule is subject to weather and unforeseen circumstances.

WEEKEND ROAD CLOSURES/TRAFFIC SHIFTS 

  • On Saturday, November 4th there will be a full closure of Massachusetts Avenue with associated detours for completion of lighting and brickwork in the portal as well as final paving activities at 4th & H and other areas as needed.

REMINDER OF WORK HOURS 

As an ongoing reminder, the contractor is adhering to prescribed work hours which include the following at Massachusetts Avenue and H Streets, NW between 2nd and 4th Streets:

  • Monday-Friday 7:00am-5pm
  • Monday-Tuesday 7:00pm-12:00 midnight, as needed
  • Saturday-Sunday 8:00am-6:00pm, as needed

Also, work in the I-395 Highway, including the new on-ramp portal being constructed at 2nd and Massachusetts Avenue is permitted for 24-Hours operation.  The highway work takes place overnight for safety reasons as there is much less traffic.

I-395 OVERNIGHT LANE CLOSURE

Note: Work in the I-395 Highway will last for the next several months.  Nighttime lane closure has been suspended until October.  Daytime lane closures remain in effect for northbound lands. If unusually loud noise occurs overnight, please email info@3rdsttunnel.com or call 202-719-0196 to report the problem.

MASS AVE. & H St. AREA NW:

  • Most work is complete in this area, however, over the next few weeks contractor will perform final installations and clean-up activities.

3RD STREET AREA NW:

  • Light evening work has been permitted and is underway on the east and south sides of Holy Rosary Church.
  • Additional site work requires ongoing single lane closure on 3rd Street. One lane of through traffic is still open at all times.

2ND STREET & I-395 TUNNEL AREA NW:

  • Periodic closures being utilized in northbound lanes during the daytime.