Construction Update/Look Ahead

22 Mar Construction Update/Look Ahead


Following is the construction Look Ahead/Weekly Forecast, for the Third Street Tunnel Infrastructure Project which outlines work activities that may impact the surrounding community, as provided by Property Group Partners (PGP). Balfour Beatty Construction DC (BBCDC), the construction manager, will make every effort to advise PGP of changes that affect the scheduled events. Schedule is subject to weather and unforeseen circumstances.

TRAFFIC & ONGOING UTILITY RELOCATION CONSTRUCTION       

As noted below, utility relocation activities continue on the surface streets and there will be intermittent street closures during the next several months, including most weekends.  While the information below describes work to take place in the area over the next two weeks, please check the Daily Traffic Impact report at www.3rdsttunnel.com and real-time traffic advisories at www.ddot.dc.gov for the latest closure and detour information.

I-395 OVERNIGHT LANE CLOSURE/CONCRETE WALL AND STEEL ERECTION:

As noted below, work in the I-395 Highway will enter a new phase that will last for the next seven months. There will be overnight lane closures and detours to accommodate the installation of pre-fab concrete wall panels in the median and then vertical steel erection. This work should not be any louder than the current overnight highway operations. However, there may occasionally be different sounds as the concrete panels and steel pieces are placed and secured. If unusually loud noise occurs overnight, please email info@3rdsttunnel.com or call 202-719-0196 to report the problem.

MASS AVE AREA NW:

  • Installation of new 30” water main on Massachusetts Avenue between 4th and 2nd Streets.
    • Additional valve shut/pipe connections at 4th and Massachusetts Avenue on March 17-20.
  • Excavation and shoring of new I-395 southbound access portal.
  • Road closures expected for the next several weekends.
  • Remaining plates at 4th and Massachusetts Avenue will be removed once DC Water tie-in and testing complete, approximately 4 weeks (end of March).


3RD STREET AREA NW:

  • Electric cable substantially complete. Backfilling and permanent paving ongoing.
  • Installation of a new 8” water main along the east side of 3rd St. from F Street to E Street.  This work is substantially complete. Chlorination testing will take place the week of March 25.
  • Backfill and paving ongoing.
  • Curb inlets and manholes being installed down 3rd Street between E and G Streets.

I-395 & 2ND STREET AREA NW:

  • Southbound lane closures scheduled for March 13-17. Closure in place from 9:00 PM to 5:00 AM each evening.
  • Steel beam installation and erection ongoing.
  • Pre-cast concrete wall installation in median ongoing.
  • South bound lane closure scheduled for March 6-10. Closure in place from 9pm to 5am each evening.
  • Installation of highway piers.
  • Installation of concrete foundation and walls for new 2nd Street off-ramp.
  • Ongoing demolition of bridge abutment and auxiliary space.