3rd Street Tunnel | Pre-Phase
15278
page-template-default,page,page-id-15278,ajax_fade,page_not_loaded,,qode-theme-ver-6.5,wpb-js-composer js-comp-ver-4.4.3,vc_responsive

Pre-Phase

 

(March 31 – June 10, 2014)

In preparation for Phase I construction activities will include the removal of existing curbs and concrete islands; installation of temporary pedestrian walkways and ramps and installation of temporary streetlights and poles along Massachusetts and H Streets, between 2nd and 4th Streets NW. Utility verification machinery will also be used to mark existing underground utilities and support structures.

 

 

Phase I – 2nd Street (May 19, 2014 – September 2015)

2nd Street between E Street and Mass Ave is closed to vehicular traffic for the duration of utility relocation series, 16 months. 2nd Street ramp will remain open. A temporary pedestrian walkway will be installed and maintained throughout the project.